Accessible version
Plain-text transcript preview
Generated by Poppler layout-aware extraction selected automatically for a malformed embedded text layer. Tables, maps, columns, and symbols may not translate perfectly.
[Page 1]
Page 2 CONNECTICUT LAW JOURNAL January 18, 2022
762 JANUARY, 2022 340 Conn. 762
Not Another Power Plant v. Connecticut Siting Council
NOT ANOTHER POWER PLANT v. CONNECTICUT
SITING COUNCIL ET AL.
(SC 20464)
Robinson, C. J., and McDonald, D’Auria,
Mullins, Kahn and Ecker, Js.
Syllabus
Pursuant to statute (§ 16-50k (a)), ‘‘no person shall . . . commence the
construction or supplying of a facility . . . that may, as determined by
the [Connecticut Siting] [C]ouncil, have a substantial adverse environ-
mental effect in the state without having first obtained a certificate of
environmental compatibility and public need . . . issued with respect
to such facility or modification by the council.’’
Pursuant further to statute (§ 16-50p (a) (3) (B)), ‘‘[t]he council shall file,
with its order, an opinion stating in full its reasons for the decision.
The council shall not grant a certificate, either as proposed or as modified
by the council, unless it shall find and determine . . . [t]he nature of
the probable environmental impact of the facility alone and cumulatively
with other facilities, including a specification of every significant adverse
effect . . . .’’
The plaintiff, a nonprofit association formed to promote environmental
conservation in the town of Killingly, appealed to the trial court from
the decision of the defendant council, which approved the application of
the defendant energy company, N Co., for a certificate of environmental
compatibility and public need in connection with an electric generating
facility that N Co. sought to construct in the town. The plaintiff had
intervened in the administrative proceeding pursuant to statute (§ 22a-
19 (a) (1)), claiming that approval of the facility would result in the
unreasonable pollution and impairment of the public trust in the environ-
ment. According to N Co.’s application, the facility would be supplied
with natural gas by E Co., which owns a distribution pipeline that extends
from a mainline to the site of the proposed facility. For the facility to
function, however, E Co. would need to replace approximately two
miles of its existing distribution pipeline with an upgraded pipeline
that would cross or abut wetlands, a river, and certain preserved or
undeveloped lands. The plaintiff moved to dismiss or to stay N Co.’s
application, claiming that the council was required to consider the envi-
ronmental impact of the upgraded pipeline when weighing the public
benefit of the facility against the harm that it would cause to the environ-
ment under § 16-50p (c) (1) of the Public Utility Environmental Standards
Act (act) and that N Co. had neither obtained a commitment as to
the design of the upgraded pipeline from E Co. nor fully assessed the
environmental impact the upgraded pipeline would have. The council
denied the plaintiff’s motion and, after hearings, approved N Co.’s appli-
[Page 2]
January 18, 2022 CONNECTICUT LAW JOURNAL Page 3
340 Conn. 762 JANUARY, 2022 763
Not Another Power Plant v. Connecticut Siting Council
cation for a certificate, without ever considering the potential environ-
mental effects of the upgraded pipeline. The council found that the
facility was necessary for the reliability of the electric power supply of
the state and, therefore, would be a public benefit, and that the adverse
impacts of the facility were not disproportionate, either alone or cumula-
tively, when compared to the public benefit. On appeal to the trial court,
the plaintiff claimed that the council had improperly segmented the
project into two components, namely, N Co.’s electric generating facility
and E Co.’s upgraded pipeline, to avoid a comprehensive review of the
project’s overall environmental impact. After rejecting N Co.’s special
defense that the plaintiff lacked standing to appeal, the trial court con-
cluded that, although the facility was intertwined with the upgraded
pipeline insofar as the facility, as planned, could not operate without
it, the council reasonably decided to consider them separately because,
under the act, electric generating facilities and fuel transmission lines
are separate facilities to be considered under different provisions and
submitted by two unrelated parties. The court also observed that E Co.
would need to apply for a certificate of environmental compatibility
and public need under § 16-50k (a) to construct the upgraded pipeline
and stated that it would consider the pipeline’s environmental impact
at that time. Further, the trial court concluded that the plaintiff had
neither pointed to any environmental concerns with the facility itself
nor claimed that combining the environmental impact of the facility with
that of the upgraded pipeline would result in an increased environmental
impact. Accordingly, the trial court rejected the plaintiff’s improper
segmentation claim, concluded that the plaintiff failed to establish that
the council had improperly approved N Co.’s application, and rendered
judgment dismissing the plaintiff’s administrative appeal. On the plain-
tiff’s appeal, held:
1. The trial court correctly concluded that the plaintiff had standing to
appeal under § 22a-19 (a) (1) from the council’s decision, the plaintiff
having asserted a colorable claim of potential impairment of or destruc-
tion to the environment by alleging in its complaint that the council’s
improper segmentation of the project into two separate components,
in order to avoid a comprehensive review of the project’s overall impact,
would result in a substantial likelihood of such impairment or
destruction.
2. The plaintiff could not prevail on its claim that the trial court incorrectly
determined that the council’s failure to consider the environmental
impact of E Co.’s future, upgraded pipeline when weighing the public
benefit of the electric generating facility against the harm that it would
cause to the environment was not arbitrary and capricious:
a. Contrary to the council’s claim, the plaintiff did not waive its claim
regarding the council’s refusal to consider the environmental impact of
the upgraded pipeline by failing to challenge the council’s finding that
the facility would provide a public benefit in the trial court; the very
[Page 3]
Page 4 CONNECTICUT LAW JOURNAL January 18, 2022
764 JANUARY, 2022 340 Conn. 762
Not Another Power Plant v. Connecticut Siting Council
reason that the plaintiff argued that the council was required to consider
the impact of the upgraded pipeline was that, if it had done so, it might
have concluded that the adverse environmental impact of the facility
and the upgraded pipeline together outweighed the public benefit, and
the plaintiff’s counsel expressly raised that argument in the trial court.
b. The council was not prohibited under the act from considering the
environmental impact of E Co.’s future, upgraded pipeline when consider-
ing N Co.’s application for a certificate for the electric generating facility;
the language of § 16-50p (a) (3) (B) specifies the environmental factors
that the council must consider and address in its written decision, a
review of the statutory scheme revealed that the act does not specify
matters that the council may not consider when balancing the public
benefit of the proposed facility against the harm it would cause to the
environment, and this court could perceive no reason why the legislature
would have wanted to prohibit the council from considering any informa-
tion that would be relevant to this balancing process; accordingly, when
determining whether a facility under review will have a public benefit,
the council is authorized to consider the facts that that facility is interde-
pendent with another facility that does not yet exist and that there is a
significant likelihood that the nonexistent facility ultimately may not
be approved because its harmful effects, considered together with the
harmful effects of the facility under review, could outweigh the public
benefit of the facilities considered as a whole; moreover, although the
council cannot, as a practical matter consider the actual environmental
impact of a future project, the nature and scope of which has yet to be
determined, the general notion that the council should weigh the overall
benefits that interdependent projects will provide to the public against
their overall impact on the environment was supported by both common
sense and federal case law disfavoring the use of improper segmentation.
c. The council’s decision not to consider the potential environmental
impact of the upgraded pipeline during the proceedings on N Co.’s appli-
cation for a certificate for the facility was not arbitrary and capricious:
although this court disagreed with the trial court’s determination that
the plaintiff did not claim that combining the environmental impact of
the electric generating facility with that of the upgraded pipeline would
result in an increased environmental impact, the plaintiff having very
clearly claimed that the sum of their effects would be greater than the
effect of either project considered alone and that the cumulative effect
should be weighed against the public benefit, the trial court correctly
determined that the council did not improperly segment the project on
the grounds that the environmental impact of the upgraded pipeline
would necessarily be considered by the council in a future proceeding
and that the risk and cost of failing to obtain approval of the upgraded
pipeline would be borne solely by N Co., which would have to post
a decommissioning bond and to develop a decommissioning plan for
[Page 4]
January 18, 2022 CONNECTICUT LAW JOURNAL Page 5
340 Conn. 762 JANUARY, 2022 765
Not Another Power Plant v. Connecticut Siting Council
restoring the facility site if the council did not ultimately approve the
upgraded pipeline.
3. The plaintiff could not prevail on its unpreserved claim that the trial court
based its conclusion that the council and N Co. did not improperly
segment the project on the incorrect assumption that, under § 16-50k
(a), E Co. would be required to apply for a certificate of environmental
compatibility and public need in connection with the upgraded pipeline;
to the extent that the plaintiff claimed that the trial court failed to
recognize that E Co. could evade the council’s review by seeking review
of the pipeline by another state or federal agency, the plaintiff made no
such claim in the trial court, where the plaintiff’s counsel expressly
stated that she had every reason to believe that the council would
thoroughly evaluate the environmental impacts of the pipeline and that
her only concern was that the council would not be evaluating the
cumulative impact of the facility and the upgraded pipeline, and, accord-
ingly, any such claim was waived; moreover, any error with respect to
the trial court’s failure to recognize that, under § 16-50k (a), E Co. could
file a petition for a declaratory ruling from the council that the upgraded
pipeline would not have a substantial adverse environmental effect,
rather than applying for a certificate of environmental compatibility and
public need, was harmless, as the statutory and regulatory provisions
governing petitions for a declaratory ruling from the council were not
facially inadequate to ensure that the council would fully and fairly
consider the issue, and any claim that the council would not do so in
the present case was not ripe for review.
(One justice concurring separately; two justices concurring
in part and dissenting in part in one opinion)
Argued September 10, 2020—officially released September 28, 2021*
Procedural History
Appeal from the decision of the named defendant
approving the application by the defendant NTE Con-
necticut, LLC, for the construction of an electric gener-
ating facility, brought to the Superior Court in the
judicial district of New Britain and tried to the court,
Cordani, J.; judgment dismissing the appeal, from
which the plaintiff appealed. Affirmed.
Mary Mintel Miller, for the appellant (plaintiff).
Robert L. Marconi, assistant attorney general, with
whom, on the brief, were William Tong, attorney gen-
* September 28, 2021, the date that this decision was released as a slip
opinion, is the operative date for all substantive and procedural purposes.
[Page 5]
Page 6 CONNECTICUT LAW JOURNAL January 18, 2022
766 JANUARY, 2022 340 Conn. 762
Not Another Power Plant v. Connecticut Siting Council
eral, and Clare E. Kindall, solicitor general, for the
appellee (named defendant).
Linda L. Morkan, with whom were Kenneth C. Bal-
dwin, James P. Ray and, on the brief, Emilee Mooney
Scott, for the appellee (defendant NTE Connecticut,
LLC).
Opinion
ROBINSON, C. J. The principal issue in this appeal
is whether the named defendant, the Connecticut Siting
Council (council), properly refused to consider the envi-
ronmental impact of installing a gas pipeline to a pro-
posed electric generating facility when weighing the
public benefit of the facility against its probable envi-
ronmental impact pursuant to the Public Utility Envi-
ronmental Standards Act (act), General Statutes § 16-
50g et seq. The defendant NTE Connecticut, LLC (NTE),
submitted an application to the council seeking a certifi-
cate of environmental compatibility and public need
for the construction of an electric generating facility
(facility) in the town of Killingly (town) pursuant to the
act. Thereafter, the plaintiff, Not Another Power Plant, a
nonprofit association formed to promote environmental
conservation in the town, intervened in the proceeding
pursuant to General Statutes § 22a-19 (a) (1).1 After
conducting hearings, the council issued a decision
approving NTE’s application. The plaintiff then appealed
from the council’s decision to the trial court, claiming
1
General Statutes § 22a-19 (a) (1) provides: ‘‘In any administrative, licens-
ing or other proceeding, and in any judicial review thereof made available
by law, the Attorney General, any political subdivision of the state, any
instrumentality or agency of the state or of a political subdivision thereof,
any person, partnership, corporation, association, organization or other legal
entity may intervene as a party on the filing of a verified pleading asserting
that the proceeding or action for judicial review involves conduct which has,
or which is reasonably likely to have, the effect of unreasonably polluting,
impairing or destroying the public trust in the air, water or other natural
resources of the state.’’
[Page 6]
January 18, 2022 CONNECTICUT LAW JOURNAL Page 7
340 Conn. 762 JANUARY, 2022 767
Not Another Power Plant v. Connecticut Siting Council
that, when weighing the public benefit of the facility
against the harm that it would cause to the environment,
the council improperly had failed to consider the envi-
ronmental impact of a gas pipeline that would have to
be installed in the future to provide fuel to the facility.
The trial court concluded that the council was not
required to consider the impact of the gas pipeline and
rendered judgment dismissing the plaintiff’s administra-
tive appeal. On appeal to this court,2 the plaintiff claims
that the council’s refusal to consider the environmental
impact of the future gas pipeline was arbitrary and
capricious. In response, the defendants disagree and
also challenge the plaintiff’s standing to bring this
administrative appeal. Although we conclude that the
plaintiff had standing, we also conclude that the trial
court properly dismissed the plaintiff’s administrative
appeal. Accordingly, we affirm the judgment of the
trial court.
The record reveals the following facts, which were
found by the council and the trial court or are undis-
puted, and procedural history. On August 17, 2016, NTE
filed with the council an application for a certificate of
environmental compatibility and public need (certifi-
cate) pursuant to General Statutes § 16-50k (a).3 NTE
explained in the application that ‘‘[n]atural gas will be
provided [to the facility] through a firm natural gas fuel
supply contract . . . .’’ The natural gas would be sup-
plied through an upgraded gas pipeline to be con-
structed and owned by Eversource Energy Service
2
The plaintiff appealed to the Appellate Court, and we granted NTE’s
motion to transfer the appeal to this court pursuant to General Statutes
§ 51-199 (c) and Practice Book § 65-2.
3
General Statutes § 16-50k (a) provides in relevant part: ‘‘Except as pro-
vided in subsection (b) of section 16-50z, no person shall . . . commence
the construction or supplying of a facility . . . that may, as determined by
the council, have a substantial adverse environmental effect in the state
without having first obtained a certificate of environmental compatibility
and public need, hereinafter referred to as a ‘certificate’, issued with respect
to such facility or modification by the council. . . .’’
[Page 7]
Page 8 CONNECTICUT LAW JOURNAL January 18, 2022
768 JANUARY, 2022 340 Conn. 762
Not Another Power Plant v. Connecticut Siting Council
Company (Eversource). Eversource currently owns and
operates an approximately fifty year old distribution
gas pipeline that extends from a mainline located
approximately two miles from the proposed facility site.
Eversource would replace the distribution pipeline with
a new pipeline with a diameter of at least fourteen
inches. NTE further explained that it was seeking autho-
rization to use ultra-low sulfur distillate as a fuel for
the facility for up to 720 hours per year, although actual
use was ‘‘expected to occur on the order of several
hours once every two to three years and only under the
circumstance where natural gas supply is not available.’’4
The plaintiff successfully sought permission to inter-
vene in the proceeding pursuant to § 22a-19 (a) (1),
claiming that approval of the facility would result in
the unreasonable pollution and impairment of the pub-
lic trust in the environment.5 Thereafter, the plaintiff
filed a motion for a stay and/or to dismiss the applica-
tion, in which it claimed that the council was required
to consider the environmental impact of the future gas
pipeline when weighing the public benefit of the facility
against the harm that it would cause to the environment,
as required by General Statutes § 16-50p.6 The plaintiff
4
The council initially denied NTE’s application without prejudice on
grounds unrelated to the plaintiff’s claims. Thereafter, NTE filed a motion
to open and modify the council’s decision. The council granted the motion
and recommenced the proceedings on NTE’s application for a certificate.
Consistent with the approach of the parties, we treat the proceedings on
NTE’s application before and after the council granted NTE’s motion to
open as a single, continuous proceeding.
5
The Connecticut Fund for the Environment also intervened in the pro-
ceedings on NTE’s application for a certificate pursuant to § 22a-19 (a) (1),
but it is not a participant in this appeal.
6
General Statutes § 16-50p provides in relevant part: ‘‘(a) (1) In a certifica-
tion proceeding, the council shall render a decision upon the record either
granting or denying the application as filed, or granting it upon such terms,
conditions, limitations or modifications of the construction or operation of
the facility as the council may deem appropriate.
‘‘(2) The council’s decision shall be rendered in accordance with the fol-
lowing:
‘‘(A) Not later than twelve months after the filing of an application for a
facility described in subdivision (1) or (2) of subsection (a) of section 16-50i
[Page 8]
January 18, 2022 CONNECTICUT LAW JOURNAL Page 9
340 Conn. 762 JANUARY, 2022 769
Not Another Power Plant v. Connecticut Siting Council
pointed out in the motion that the new pipeline would
cross or abut (1) large wetland areas, (2) open space
and protected land held by the Wyndham Land Trust,
(3) the Bafflin Sanctuary, which is owned by the Con-
necticut Audubon Society, and the Air Line State Park
Trail, (4) a large, undeveloped parcel owned by the
Pomfret Rod and Gun Club, and (5) the Quinebaug
River. The plaintiff also pointed out that NTE had not
obtained a firm commitment as to the design and con-
or subdivision (4) of said subsection (a) if the application was incorporated
in an application concerning a facility described in subdivision (1) of said
subsection (a); and
‘‘(B) Not later than one hundred eighty days after the filing of an applica-
tion for a facility described in subdivisions (3) to (6), inclusive, of subsection
(a) of section 16-50i, provided the council may extend such period by not
more than one hundred eighty days with the consent of the applicant.
‘‘(3) The council shall file, with its order, an opinion stating in full its
reasons for the decision. The council shall not grant a certificate, either as
proposed or as modified by the council, unless it shall find and determine:
‘‘(A) Except as provided in subsection (b) or (c) of this section, a public
need for the facility and the basis of the need;
‘‘(B) The nature of the probable environmental impact of the facility alone
and cumulatively with other existing facilities, including a specification of
every significant adverse effect, including, but not limited to, (i) electromag-
netic fields that, whether alone or cumulatively with other effects, impact
on, and conflict with the policies of the state concerning the natural environ-
ment, (ii) ecological balance, (iii) public health and safety, (iv) scenic,
historic and recreational values, (v) agriculture, (vi) forests and parks, (vii)
air and water purity, and (viii) fish, aquaculture and wildlife;
‘‘(C) Why the adverse effects or conflicts referred to in subparagraph (B)
of this subdivision are not sufficient reason to deny the application . . . .
***
‘‘(c) (1) The council shall not grant a certificate for a facility described
in subdivision (3) of subsection (a) of section 16-50i [i.e., any electric generat-
ing or storage facility], either as proposed or as modified by the council,
unless it finds and determines a public benefit for the facility and considers
neighborhood concerns with respect to the factors set forth in subdivision
(3) of subsection (a) of this section, including public safety.
***
‘‘(3) For purposes of this section, a public benefit exists when a facility
is necessary for the reliability of the electric power supply of the state or
for the development of a competitive market for electricity and a public
need exists when a facility is necessary for the reliability of the electric
power supply of the state. . . .’’
[Page 9]
Page 10 CONNECTICUT LAW JOURNAL January 18, 2022
770 JANUARY, 2022 340 Conn. 762
Not Another Power Plant v. Connecticut Siting Council
struction of the new pipeline and had not fully assessed
the environmental impact that it would have. Accord-
ingly, the plaintiff contended that the council should
dismiss NTE’s application or stay proceedings on it
until the council could consider Eversource’s applica-
tion with respect to the pipeline. The council denied
the motion on the ground that ‘‘the application was
deemed complete by the [c]ouncil on September 15,
2016, and the feasibility of the utility interconnections
will be explored during the course of these proceedings.’’
During the hearings on NTE’s application, counsel
for the plaintiff asked counsel for NTE, Mark Mirabito,
whether it was ‘‘fair to say that with respect to th[e]
gas pipeline . . . there’s no evidence in th[e] record
before [the council] for [it] to determine what impacts
. . . installation of this gas pipeline will have . . . on
the wetlands, open space, state park and land trust lands
and the Quinebaug River . . . .’’ Another attorney for
NTE, Kenneth C. Baldwin, objected to the question on
the ground that ‘‘the [c]ouncil has already determined
that it will review those impacts at a future time in an
application filed by the appropriate party, in this case,
Yankee Gas.’’7 The council’s chairman, Robert Silvestri,
stated, ‘‘that is correct.’’ Counsel for the plaintiff then
asked for clarification as to whether the council would
be considering the environmental impact of the new
pipeline. Counsel for the council, Melanie A. Bachman,
stated that, ‘‘throughout the proceeding, [the council
has] had discussions that the pipeline would be the
subject of a petition from Yankee Gas if this application
is approved. . . . However, [the council is] not even
sure if [it is] going to approve the application, or [theThis is the opening portion of a long document. Use Download complete plain text above for the full extracted transcript.

